A translator added images to their project and then tried to do an Internet S/R. It was 100+ MB, so he cancelled it (slow/expensive internet).

He also tried a Network Shared Folder S/R to a network share on our center, but it failed after a few minutes a couple of times. This could be partially due to a slow DSL connection from his home and it may work better if he tried it on a faster network on our center. We haven’t tested that yet.

Is there any way to get around the large S/R? Can he delete the images or insert reduced size images or anything? I think in the past, even if you delete images, they go into the project history and are therefore included in future S/R’s.

Thanks,

SIL+LSS+PNG

[cid:[Email Removed]]

SIL+LSS+PNG
Language Technology Consultant
SIL PNG Language Resources
Ukarumpa EHP 444 | Papua New Guinea
[Email Removed].pgmailto:[Email Removed].pg

image

较早的帖子 - 以原始语言显示
Paratext 中 由 (411 分) 发布
已重新显示 | 349 次浏览

1 个回答

0 票

It turns out that the translator only inserted 80 images at about 200 KB each into their project. But… they thought that it would work to copy all 1000 images they might use to the “figures” folder for their project. Those 1000 images were about 125 MB.

It seems that Paratext wants to S/R the whole figures folder. He tried renaming it and moving it, but Paratext still wants to S/R the whole 125 MB.

Is there a way to reverse this and remove the images he doesn’t need from the S/R and the history?

Thanks,

SIL+LSS+PNG

较早的帖子 - 以原始语言显示
由 (411 分) 发布
已重新显示

I don't have an answer for this problem. However, for future reference...

You're not supposed to add figures into a project folder that aren't yet inserted in the project. However, the project\figures folder gets S/Red. The folder project\local\figures is where full-sized image files get placed; this folder is not included in S/R. A thumbnail is automatically created & placed into project\figures, which is shared so that all users can see the thumbnails on their computers. Only the computer used for inserting the figures into a project has the full-sized image files in project\local\figures, but this folder can be copied manually to another computer if desired. This (local) folder is needed for decent printing of portions from the project.

KimB

较早的帖子 - 以原始语言显示

Hi SIL+LSS+PNG,

If you need to keep your change history and still delete unwanted
files from the history, then the only way that I am aware of is to:


 (i) delete the images [so they are not shared anymore] 


and then 


(ii) use Tools &gt; Advanced &gt; <b>Convert Project.</b>  Then
ensure that the option to "Remove deleted files from project
history" is checked. I have a feeling that this feature is only in
7.6(beta), but it might have been there since 7.5 (I'm not sure).




I hope that helps.


Mark
较早的帖子 - 以原始语言显示

If the changes have not been shared - which seems to be the case - then a
tool like TortoiseHg can be used to remove history. Once changes have been
shared, the Convert Project tool is the only solution - this is because any
history removed from the local copy will just be retrieved again during
send/receive.

Just deleting the files or renaming the folders isn’t sufficient since the
copies of the files will still be in history.

I found some pages with instructions by searching for “tortoisehg strip
history”.

John+Wickberg
Paratext Support

较早的帖子 - 以原始语言显示

相关问题

0 票
1 个回答 293 次浏览
One project here has two main users - admin using Windows; translator using Linux. They just started using PT8, with the ... elsewhere and pick up a virus along the way). Thanks.
anon310851 135 发布 提问于 一月 3, 2018
0 票
1 个回答 333 次浏览
我们希望顾问能看到我们使用的图像,所以我们将它们直接放在回译(Back Translation)中 逐词对照(interlinear)功能会将 \fig 代码直接插入到回译文本中,但如果不将 figures 文件夹从父项目复制到子项目,图像就不会显示出来 ... 让回译项目(或其他子项目)在父项目的图像文件夹中查找图像,那就太好了 也许已经有这样的选项了?
viverechristus 296 发布 提问于 八月 24, 2021
0 票
2 个回答 871 次浏览
L.S. 正如 lingtrans wiki 页面所解释的,可以使用 \fig Paratext 中的位置字段来指示图像是用于打印 应用程序还是网络 该 wiki 页面引用了以下文档,原文如下: 您的排版人员/应用程序创建者需要使用类似 ... goodgoan 附言:我也在 SAB 论坛上发布了此帖,并希望在这里也能得到一些关于正则表达式的建议 提前致谢
goodgoan 347 发布 提问于 五月 3, 2021
0 票
1 个回答 187 次浏览
我在一个正在进行检查的项目中拥有 顾问 (Consultant)权限 今天早上,我的 S/R 结果框显示我对 属性和设置 (Properties and Settings)进行了更改,但我完全不知道为什么 我没有对 属性和设置 做任何更改,而且我也无法 ... 有人会想入侵我的 PT 仅仅为了在一个冷门的 BT 项目中做更改,但我确实想确保这不是安全问题 )
Amanda T 134 发布 提问于 七月 24, 2024
0 票
1 个回答 230 次浏览
我刚刚在一台一年多没有进行过 S/R 的计算机上执行了 S/R。 我们收到了 58 条冲突通知,其中 43 条显示“对章节的更改无法合并,因为节文衔接不同。”当我检查这些不同的章节时,只有一个章节存在节文衔接,并且该章节并未被修改。我看不出导致该冲突消息出现的其他原因。有什么建议吗? anon554738
Kevin Nicholas 142 发布 提问于 二月 18, 2023
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
Accept the one whose faith is weak, without quarreling over disputable matters.
Romans 14:1
3,052 个问题
6,011 个回答
5,677 条评论
2,031 位用户