0
182 次瀏覽

Hi,
I am looking at implementing project plans etc. on existing/mature projects, but one issue that I am having difficulty with is recording the progress of previously completed material. For instance, as a part of a project plan, we would like to include the BT checks, etc. However, much of our material (which was translated and then imported into Paratext), doesn’t have a corresponding BT in Paratext. At present, I don’t see a way to “grandfather” in parts of a project that were previously completed. For example, about half of our NT in my project was translated before we started using Paratext. So, the BT is not there, though the material is finished and printed. I don’t really see any straightforward way to mark those books as complete. I think I could remove the BT checks, mark the progress as complete, and then add the BT checks back into the project plan, but that gets complicated for many users.
Thanks
BEH

舊文章 - 以原文顯示
Paratext (418 點) 提出 | 182 次瀏覽

2 個回答

+1
最佳回答

This morning I have been working on generating a project plan for my organization, and I have noticed a couple of things. Especially in the early days of Translation, we are translating book portions, not complete books.
In setting up the project plan, I wanted to set the stages to be able to begin after the previous Stage was complete for the chapters being translated at the time, (some of the stage tasks are able to be done simultaneously). If I set tasks to be able to start after a previous stage was complete, it requires that all chapters in the stage be complete, but if I allow it to start after the previous task was completed, I have the option of selecting completion by chapter.
Would it be feasible to also include the Stage chapter option?
If not, the after previous stage by chapter option is a workable solution.
Thanks
Incidentally, I noticed an easy way to bypass the issue of imported/mature material not passing all the checks, due to missing BT’s etc…Our NT had already been finished, but many of the BT’s were not in Paratext, causing it to fail the BT checks. However, in Assignments and Progress, by changing the view to Stages Table, I could check that all stages were complete, which then reports the progress as complete in the Progress chart. In the Stages table it still showed the issues that it encountered because of the checks, but it didn’t affect the ability to mark the stage as complete.

舊文章 - 以原文顯示
(418 點) 提出
已重新顯示
0
舊文章 - 以原文顯示
[Expert]
(2.9k 點) 提出

相關問題

0
3 個回答 289 次瀏覽
(System: Win7x64 SP1, PT8 v56) Several projects here use two BTs. The primary BT is the local majority language, and the ... use Option 2, because Option 1 is a lot of work.
listentwice 1.2k 提出 已提問 4月 23, 2018
0
1 個回答 230 次瀏覽
L.S. I have been struggeling to get this added material working, can you guide me along 1 the first is kpasin ... to the _|_kpasin. Any ideas? Thanks in advance, goodgoan
goodgoan 347 提出 已提問 5月 5, 2020
0
1 個回答 29 次瀏覽
有沒有辦法可以同時檢視並編輯實際文本及其回譯的聖經術語(Biblical Term)?這樣會非常有帮助,最好能在同一個視窗中完成!看起來似乎做不到,但有沒有好的替代方案? 謝謝!
Roland 245 提出 已提問 2月 2
0
4 個回答 696 次瀏覽
I have one Paratext install that is displaying extra slashes in many resources and the BT draft as well. I go to the BT ... something, but don't know how to fix it. Any ideas?
listentwice 1.2k 提出 已提問 3月 9, 2018
0
1 個回答 311 次瀏覽
In the last couple of days I have noticed that I am not able to make any changes to the roles and permissions on ... add a user to a BT project without any difficulty. Thanks BEH
BEH 418 提出 已提問 9月 1, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
And over all these virtues put on love, which binds them all together in perfect unity.
Colossians 3:14
3,045 個問題
6,005 個回答
5,671 則評論
2,026 位使用者