This morning I have been working on generating a project plan for my organization, and I have noticed a couple of things. Especially in the early days of Translation, we are translating book portions, not complete books.
In setting up the project plan, I wanted to set the stages to be able to begin after the previous Stage was complete for the chapters being translated at the time, (some of the stage tasks are able to be done simultaneously). If I set tasks to be able to start after a previous stage was complete, it requires that all chapters in the stage be complete, but if I allow it to start after the previous task was completed, I have the option of selecting completion by chapter.
Would it be feasible to also include the Stage chapter option?
If not, the after previous stage by chapter option is a workable solution.
Thanks
Incidentally, I noticed an easy way to bypass the issue of imported/mature material not passing all the checks, due to missing BT’s etc…Our NT had already been finished, but many of the BT’s were not in Paratext, causing it to fail the BT checks. However, in Assignments and Progress, by changing the view to Stages Table, I could check that all stages were complete, which then reports the progress as complete in the Progress chart. In the Stages table it still showed the issues that it encountered because of the checks, but it didn’t affect the ability to mark the stage as complete.