0 votos
183 visualizações

:warningicon: This can only be done by a project administrator.

Follow the steps below to specify the books for which you want to track project progress:

  1. From the Project menu, select Project Properties and Settings....
  2. On the "Books" tab, do either or both of the following:
    • Select the books for which you want to track progress.
    • Deselect the books for which you do not want to track progress.
      Deselecting a book does NOT remove it from the project.
  3. Click OK.

Project progress is calculated based on the total number of verses in the books that you specified.

Books without verses (for example, a glossary) cannot be tracked for project progress.

:informationicon: See also:

Publicação antiga - exibida no idioma original
Paratext por [Expert]
(735 pontos)

reexibida | 183 visualizações

Por favor, faça login ou registre-se para responder a esta pergunta.

Perguntas relacionadas

0 votos
1 resposta 284 visualizações
Várias das nossas equipes acabaram de começar a usar um Plano de Progresso e estavam se perguntando como rastrear seleções ... seu status visível por meio de um plano de progresso?
anon251522 150 perguntada Abr 4, 2023
0 votos
1 resposta 268 visualizações
When project was created and the tracking of the project progress was started, the project had the versification English ( ... that's the only possible solution I can think of.
lichti 872 perguntada Fev 13, 2017
0 votos
0 respostas 149 visualizações
To include a check in a stage of project progress: From the Project menu, select Project Plan.... Click the Checks ... -checks-can-i-include-in-a-stage-of-project-progress/1217)
[Expert]
anon421222
735
perguntada Fev 23, 2017
0 votos
0 respostas 233 visualizações
Normally, you should be an administrator to do this. By default, all administrators, translators, and consultants ... The Send/Receive Projects dialog appears; click Send/Receive.
[Expert]
anon421222
735
perguntada Fev 23, 2017
0 votos
1 resposta 207 visualizações
Yes, in the Users, Roles and Permission window click on the Other Permissions button and uncheck the Progress box. In ... or remove permission for certain project tasks? in help.
[Expert]
Jeff_Shrum
2,9k
perguntada Mai 10, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
For just as each of us has one body with many members, and these members do not all have the same function, so in Christ we, though many, form one body, and each member belongs to all the others.
Romans 12:4-5
3,052 perguntas
6,011 respostas
5,677 comentários
2,031 usuários