Follow the steps below to specify the books for which you want to track project progress:

  1. From the Project menu, select Project Properties and Settings....
  2. On the "Books" tab, do either or both of the following:
    • Select the books for which you want to track progress.
    • Deselect the books for which you do not want to track progress.
      Deselecting a book does NOT remove it from the project.
  3. Click OK.

Project progress is calculated based on the total number of verses in the books that you specified.

Books without verses (for example, a glossary) cannot be tracked for project progress.

:informationicon: See also:

Postingan lama - ditampilkan dalam bahasa aslinya
Paratext oleh [Expert]
(735 poin)

ditampilkan kembali | 183 tampilan

Silakan masuk atau daftar untuk menjawab pertanyaan ini.

Pertanyaan terkait

0 suara
1 jawaban 284 tampilan
Beberapa tim kami baru saja mulai menggunakan Rencana Progres dan bertanya-tanya bagaimana cara melacak pilihan ... saran untuk membuat statusnya terlihat melalui rencana progres?
anon251522 150 bertanya Apr 4, 2023
0 suara
1 jawaban 268 tampilan
When project was created and the tracking of the project progress was started, the project had the versification English ( ... that's the only possible solution I can think of.
lichti 872 bertanya Feb 13, 2017
0 suara
0 jawaban 149 tampilan
To include a check in a stage of project progress: From the Project menu, select Project Plan.... Click the Checks ... -checks-can-i-include-in-a-stage-of-project-progress/1217)
[Expert]
anon421222
735
bertanya Feb 23, 2017
0 suara
0 jawaban 233 tampilan
Normally, you should be an administrator to do this. By default, all administrators, translators, and consultants ... The Send/Receive Projects dialog appears; click Send/Receive.
[Expert]
anon421222
735
bertanya Feb 23, 2017
0 suara
1 jawaban 207 tampilan
Yes, in the Users, Roles and Permission window click on the Other Permissions button and uncheck the Progress box. In ... or remove permission for certain project tasks? in help.
[Expert]
Jeff_Shrum
2,9k
bertanya Mei 10, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
Very truly I tell you, whoever accepts anyone I send accepts me; and whoever accepts me accepts the one who sent me.
John 13:20
3,052 pertanyaan
6,011 jawaban
5,677 komentar
2,031 pengguna