How do we set the default view of Assignments & Progress to show All Tasks. I have multiple users who are constantly looking at My Tasks, but the way we work together in our program, it is best for everyone to always be looking at All Tasks.

I know the default view can be changed, because it always opens up as All Tasks for me, but other users always have it open up to My Tasks.

Publicación antigua - se muestra en su idioma original
Paratext por (280 puntos)
mostrada de nuevo | 231 vistas

1 Respuesta

0 votos
Mejor respuesta

The way that A&P opens is determined by your role. For an Administrator it always opens to All Tasks. For a Translator it always opens to My Tasks.

Publicación antigua - se muestra en su idioma original
por [Expert]
(9,9k puntos)

I am going to suggest to the developers that this be made an option that can be changed. Do people have reasons for or against? For the context that I’m working in, it works best for the users to be looking at the All Tasks view all the time. They themselves are the ones assigning the various tasks to themselves. They work together to decide who is going to do what. But they also need to be aware of what the other teammates are doing, and they need to work together to do all the tasks and checks from the top to the bottom. Sometimes a particular teammate is absent, in which case, the other teammates need to still also complete tasks that they had previously assigned to him. So looking at the My Tasks view simply confuses the issue and contributes to a lack of communication, and also to tasks and checks being skipped.

Publicación antigua - se muestra en su idioma original

Preguntas relacionadas

+1 voto
3 respuestas 463 vistas
Is there any way to hide the Assignments & Progress icon in a given project? It’s somewhat in the way if one’s not using this function…
Paulus Kieviet 517 preguntada jun 1, 2018
0 votos
3 respuestas 950 vistas
He configurado muchos proyectos utilizando un plan de proyecto. Sin embargo, tengo un proyecto en el que, al abrir ... proyecto tiene muchos libros vacíos que no se han iniciado
Kent Spielmann 1,8k preguntada mar 9, 2023
0 votos
2 respuestas 332 vistas
After updating to 8.0.100.45 it looks like Assignments and Progress has stopped working. It was resolved by uninstalling update ... going back to 38. 2018-01-19.jpg1920 1080 524 KB
Iver Larsen 869 preguntada ene 19, 2018
0 votos
1 respuesta 450 vistas
There is a good help page about assigning tasks and checks to members of a team at [Link Removed] But this ... , Gospels, Epistles. Thanks for thinking about this idea. anon981039
anon981039 118 preguntada ene 5, 2018
0 votos
1 respuesta 202 vistas
Hola, Les escribo en nombre de un compañero de equipo que está teniendo un problema extraño con el ... ventana de Assignments and Progress? Cualquier ayuda será apreciada.
KmSilvey 109 preguntada nov 14, 2022
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
There is neither Jew nor Gentile, neither slave nor free, nor is there male and female, for you are all one in Christ Jesus.
Galatians 3:28
3,060 preguntas
6,021 respuestas
5,689 comentarios
2,035 usuarios