This team reports that they can’t proceed with the migration because after the step where they fill out the webform, they return to Paratext and it can’t make the connection. I don’t know if it is timing out or what. Is there a way to preregister the project which might enable it to make the connection?

Старое сообщение — показано на исходном языке
Paratext от [Moderator]
(1,3тыс. очков)

снова показан | 292 просмотров

3 Ответов

0 голосов
Лучший ответ

There is no way to have Paratext know a project is registered without using the Internet, sorry. They can do an offline migration, but the project will be considered unregistered until they can connect to the internet.

Старое сообщение — показано на исходном языке
от [Expert]
(16,7тыс. очков)

Internet improved and they succeeded. But I am still concerned about other situations. You mention an offline migration, but that isn’t possible with a shared project. I was just thinking that there might be a way to pre-register a project, since many projects were pre-registered by their organizations some time ago.

Старое сообщение — показано на исходном языке

You can do an offline migration of a shared project by telling Paratext not to access the Internet by disabling it in Tools > Options (or, slightly more difficult, by having Paratext completely fail to contact the Internet).

Старое сообщение — показано на исходном языке
+1 голос

Would this also be a way that one could rename a project, without having to do the conversion in Paratext 7.6? Basically, turn off the internet in Tools>Options, and then offline migrate, convert the project, delete the initially migrated project, and then register the converted/renamed project?
I tried to test this, and all appeared to work well (I didn’t actually register the project). I am trying to figure out a good way to help people rename improperly named projects, without registering the improper name, and without needing to have them install Paratext 7.6.
Thanks
BEH

Старое сообщение — показано на исходном языке
от (418 очков)

Yes, that process should work just fine for renaming a project.

Just remember that there is, then, no corresponding project in Paratext 7, so there is no way to re-do the migration and get the same project as a result (i.e. every time Convert Project is used, it will create a new project with a different internal ID). This means, even if you re-converted to the same project name, none of the Paratext servers would “see” it as the same project as the original conversion.

Most of the time, this shouldn’t be an issue, but if you are planning on pre-registering the project before a final migration or something like that, it wouldn’t work.

Старое сообщение — показано на исходном языке

Thanks, that is good information to think about.

Старое сообщение — показано на исходном языке
0 голосов

Another issue is if in poor bandwidth the team will be able to do the first send/receive, since it means uploading the entire project to the Paratext 8 server. Often upload speeds are slower than download speeds.

I helped some PNG colleagues migrate because of this issue. They added me as admin to their P7 project, I did the registration and migration and they received the new project from the 8 server. This process could be blocked by pre-registration in 8, because the 8 project won’t have the “new” admin listed as a team member, and cannot register it as a new project. To get past this someone would have to delete the preregistered project from the registry, or add the new admin to it (if it is possible to add a new team member directly to the registry without using Paratext).

Старое сообщение — показано на исходном языке
от [Expert]
(3,3тыс. очков)

Похожие вопросы

0 голосов
1 ответ 172 просмотров
Мне нужна помощь с проблемой, связанной с идентификаторами языков. Проект PT NYYBT, идентификатор языка - nyy-Latn-002 Он ... Это связано с тем 002 ? Спасибо за любую помощь
anon673293 106 задал вопрос дек 26, 2023
0 голосов
3 ответов 305 просмотров
One of my colleagues had difficulty installing Paratext 9; the program suggested contacting support with the attached log ... ! Paratext_9.0.100_20200116015808.log.pdf (55.5 KB)
anon773589 194 задал вопрос янв 16, 2020
0 голосов
0 ответов 188 просмотров
To move a book from one difficulty level to another, see either of the following: [How do I change the expected rate ... /520) (the Change the difficulty level of a book section)
[Expert]
anon421222
735
задал вопрос фев 23, 2017
0 голосов
1 ответ 157 просмотров
When I migration Consultant projects, I need to turn on the S/R and then manually re-add in all the users/roles ... Is this how it is supposed to work/migrate? Thanks, listentwice
listentwice 1,2тыс. задал вопрос ноя 8, 2017
0 голосов
2 ответов 348 просмотров
We have some projects that have used the Project Progress tool in Paratext 7. In migrating to Paratext 8, is ... ? Can it be transferred into the Project Plan? anon980192
anon980192 119 задал вопрос ноя 2, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
So Peter was kept in prison, but the church was earnestly praying to God for him.
Acts 12:5
3,045 вопросов
6,005 ответов
5,671 комментариев
2,026 пользователей