I applied notes from one project to another using the “Multi” feature. I was careful to set each tag to the same “Priority” tag and to assign each one to “Team” in the other project.

However, the next time I opened Paratext (after a closing and opening S/R), most of those tags had been reset to “To Do.”

Did I miss a step in the way I applied the notes to the other project?

Thanks,
anon180868

Publicación antigua - se muestra en su idioma original
Paratext por (195 puntos) | 598 vistas

2 Respuestas

0 votos
Mejor respuesta

Both projects have a tag named “Priority”? When I try this, the tag name is repeated in the second project and doesn’t change when I restart.

Is it possible someone else on the team changed the tag names in the second project and you received that change just before you noticed the notes had gone back to “To Do?”

Publicación antigua - se muestra en su idioma original
por [Expert]
(3,3k puntos)

Yes, both projects have the same set of tags.

There are others adding new notes in the second project, but they are not setting them to the “To Do” tag. And no one else is working in the same books in the second project.

For me, this has happened more than one time over a period of several days work.

Thanks,
anon180868

Publicación antigua - se muestra en su idioma original
0 votos

Did the second project have the priority tag available in their notes before you did this? I can imagine that if the priority tag was not defined the same in the second project via the Project Properties menu before you took these steps, they would default to the only preset tag of ToDo.

Publicación antigua - se muestra en su idioma original
por (1,3k puntos)
mostrada de nuevo

Yes, both projects had the same set of tags available at the time I applied the notes to the second project.

Thanks,
anon180868

Publicación antigua - se muestra en su idioma original

Just thought I would add this additional info:

Today, I am applying Priority 2 notes from one project to another. After a S/R, the icons in the second project are also changed to the default flag. I haven’t tested the other tags in the projects to see if it changes all of them.

I can open each note in the second project and change it to the correct icon that remains after a S/R. However, I’m trying to avoid the double work.

Would it be helpful if I send an error report with screen shots of the steps I am using?

Thanks, anon180868

Publicación antigua - se muestra en su idioma original

My apologies. I never mentioned that I was still working in PTX 8.

I tried it in PTX 9, and it seems to be working as expected.

Thanks again,
anon180868

Publicación antigua - se muestra en su idioma original

Preguntas relacionadas

0 votos
2 respuestas 351 vistas
Cuando copio notas desde un proyecto de notas de consultoría a otro proyecto (usando la función Multi ), a veces ... Original para la versificación. Qué más podría estar mal?
andre4w 155 preguntada nov 5, 2021
+1 voto
2 respuestas 387 vistas
Estoy haciendo mis notas en un proyecto de notas de consultor y copio algunas de ellas al proyecto real con ... donde estas preguntas hayan sido respondidas? Muchas gracias!
andre4w 155 preguntada oct 14, 2020
0 votos
0 respuestas 182 vistas
Intenté cambiar el tamaño de la fuente tanto modificándola en la configuración del idioma como utilizando la función de ... tener que hacer esto todo el tiempo? Gracias, anon899536
UJ 162 preguntada sep 30, 2020
0 votos
0 respuestas 170 vistas
What I have missed in pt8 and would be nice to get back in pt9 is the jump to toolbox feature. This was ... inability to import interliniarised texts. But that is a separate issue.
goodgoan 347 preguntada ago 31, 2019
0 votos
2 respuestas 986 vistas
The instructions for 7.6β say: You must ensure that the other members of the project team have upgraded Paratext before ... for sure that they really were on the latest version.
wdavidhj 1,4k preguntada jun 18, 2015
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
And I tell you that you are Peter, and on this rock I will build my church, and the gates of Hades will not overcome it.
Matthew 16:18
3,060 preguntas
6,021 respuestas
5,689 comentarios
2,035 usuarios