0 votes

Today, I applied a modified Compact Project Plan to a Project using PT8, it warned that all other project users must be using 8.0.100.76 or newer.

We often have users reinstall PT8, and not fully grade to the latest.

What happens if one of the team members is not using 8.0.100.76 or newer?
Does it hurt anything? Or just affect their ability to view or interact with the plan?

Thanks

Paratext by (1.2k points)
reshown

1 Answer

0 votes

Until they update their Paratext, they cannot send & receive with computers that have applied the project plan. If the plan has been sent to the Paratext server, they will not be able to do a s/r to the server. It is highly recommended to wait until all computers are up to date on their Paratext version before activating a project plan.

anon307241

SIL PNG

by (228 points)
reshown

Related questions

0 votes
3 answers
0 votes
7 answers
Paratext Jun 19, 2019 asked by jeffh (1.3k points)
0 votes
1 answer
0 votes
1 answer
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.