I was wondering if it is possible to unlink a daughter project and change to a standard project in PT8? In the Project, Properties and Settings is greyed out in one test I did, in the other it lets me change the Project Type, but the OK button is still greyed out.

I’m helping a project that needs to unlink the parent/daughter because they found out that the versification for parent and daughter need to be different. What’s the best way to do that in a way that preserves the most information:

  1. Convert project to preserve original setup, unlink
  2. Backup/Restore to new project, manually export/import spelling, renderings, etc

Thanks,

Stevan

较早的帖子 - 以原始语言显示
Paratext (128 分) 发布
已重新显示 | 822 次浏览

6 个回答

0
最佳答案

Beware that doing this will break all connections with the base project so they will not be able to easily determine when the base project text is changed (i.e. all the status boxes will be gone). Status boxes are very useful to a derived project so I would make certain that they need to use a different versification before preceding.

That being said, the easiest way to change to a Standard Project without losing anything else is to close Paratext and open the Settings.xml file inside the project folder and change the line:
"<TranslationInfo>Daughter:{baseProj}:{LongString}</TranslationInfo>
into:
<TranslationInfo>Standard::</TranslationInfo>".

EDIT: This should only be done by advanced users.

较早的帖子 - 以原始语言显示
[Expert]
(16.7k 分) 发布

已重新显示

Thank you! Your suggestion to modify this line in the Settings.xml file seemed to work. I have now been using our project several days with this changed Settings.xml file and everything seems to work fine.

较早的帖子 - 以原始语言显示
0

A post was split to a new topic: Can normalization setting be changed without losing all project history

较早的帖子 - 以原始语言显示
[Expert]
(16.7k 分) 发布
0

Can this same trick be used to change a Standard project to a Daughter project?

较早的帖子 - 以原始语言显示
(1.8k 分) 发布

Yes, this should also work to change a Standard project into a Daughter project. In my example above, the {baseProj} must be the short name/abbreviation of the base project and the {LongString} must be set to the <Guid> entry of the settings file in the base project.

Note that changing between project types is usually not a good idea because of the project registrations from the Paratext Registry. However, because both a Standard project and a Daughter project both have to be registered in the Paratext Registry, this particular scenario works.

较早的帖子 - 以原始语言显示

I have changed a Standard project to a Transliteration project using the method listed here, but it is still showing up in the Registry. Other project which were initially created using a project type that was a sub-project of a different project never showed up in the Registry. Is there some way to remove this one I’ve converted?

My main purpose for changing the type was so that it wouldn’t clutter our service groups audits of the different projects under their supervision.

较早的帖子 - 以原始语言显示
0

You aren’t able to just delete the entry in the Registry?

较早的帖子 - 以原始语言显示
[Expert]
(16.7k 分) 发布

The issue is converting it from a project that has its own registration to one that inherits the registration of it’s base project. I am not sure how I would do that. Since registering a project puts the project on the S/R server, unregistering it usually removes it from the S/R server, I do not want to do that. What I want to do is to transfer the project’s registration to the Base project. So if someone could give us a step by step on how to do this it would be helpful.

较早的帖子 - 以原始语言显示

I think that what I would do is the following:
Starting with a Registered Standard Project and changing it to a project that gets its registration from a base. This presumes that the base project has not been registered.

  1. Make sure you do S/R of any projects so that you have all the data on your computer.
  2. Open the Standard Project and Delete the project (Keep only my project, delete for others, delete registration). This should remove the registration and remove it from the S/R server. You need to have all users remove their copies.
  3. Register the Base project, share and do S/R
  4. Set the original project to the desired type, share it and S/R.
较早的帖子 - 以原始语言显示

This was the sort of thing that made me worry about just doing this. However based on the replies here I bit the bullet and tried. It appears that anon848905’s instructions work (meaning you don’t have to edit the Settings.xml file manually), and it appears that other users will receive the updated changes without needing to delete their project.

The only thing I didn’t confirm is whether they absolutely need to do a S/R before someone starts this process. My guess is that doing that might be a wise precaution, but probably isn’t necessary.

较早的帖子 - 以原始语言显示

The reason for suggesting that the person doing these steps does a S/R before starting is to insure that they have the latest files from the server. Since the process involves removing the files from the server you want to make sure you have them before you start. Generally it is a good idea to do S/R regularly so it might not be needed if one has been done, but it is just good practice.

较早的帖子 - 以原始语言显示

Sorry, my statement was badly worded and didn’t convey what I intended.

I completely agree that the person doing this change ought to do a S/R before deleting the server copy.

What I meant to say is that I don’t think other members need to so a S/R before the administrator does this process.

较早的帖子 - 以原始语言显示

Just to clarify - before doing a process that involves removing a project from the server, I would highly recommend that everyone on the team do a S/R and the administrator doing the process should be the last to S/R so that they get all the changes from all the team members.

较早的帖子 - 以原始语言显示
0

You should be able to delete the entry in the Registry for the project (this will also delete it off the S/R server) and then be able to S/R the project with its new type and everything should just work. Since the project ID and everything else won’t change, all the history should remain intact and users that had the previous version should just be able to S/R to get the updated project type.

较早的帖子 - 以原始语言显示
[Expert]
(16.7k 分) 发布

已重新显示
0

Thanks, Sounds like it will work.

较早的帖子 - 以原始语言显示
(1.8k 分) 发布

相关问题

0
2 个回答 67 次浏览
之前我问过一个几乎相反的问题,并收到了非常有价值的建议 那个问题 我并不是想打扰大家,如果您想了解我们为什么会有这个新问题,请阅读帖子底部 现在到了 2026 年,团队正在思考,是否有简单且安全的方法,将他们高度成熟的 PTXPrint ... 以获取新数据,何时解除链接以保持数据稳定 希望这说得通 如果我们的工作流程完全错误,请大声指出 请客气一点
Tim 934 发布 提问于 五月 29
0
2 个回答 241 次浏览
我希望子项目拥有与父项目相同的已批准拼写和已批准译法。
JeffSHR 110 发布 提问于 八月 15, 2024
0
1 个回答 147 次浏览
我是标准项目的管理员,该项目关联了许多辅助项目,而我并非这些辅助项目的管理员。我希望删除所有项目(标准项目和辅助项目),而不需要联系最初设置这些项目的管理员。该怎么做?谢谢。
Jeremy Lang 103 发布 提问于 二月 12, 2025
0
1 个回答 198 次浏览
Paratext 9.2.102.4 解决了我在 9.2.102.3 中遇到的 Interlinearizer 问题。更新后的版本支持输出到标准项目,而不仅仅是子项目。请问新版本何时会正式发布?
Iver Larsen 869 发布 提问于 一月 21, 2022
0
3 个回答 514 次浏览
Dear all I wanted to convert a Consultant Notes created using Standard Translation Project (Not Registered) to a ... Project Please help if you know the solution blessings binoy
binoy 327 发布 提问于 五月 22, 2020
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
And I tell you that you are Peter, and on this rock I will build my church, and the gates of Hades will not overcome it.
Matthew 16:18
3,048 个问题
6,007 个回答
5,672 条评论
2,028 位用户