0
300 次瀏覽

This team reports that they can’t proceed with the migration because after the step where they fill out the webform, they return to Paratext and it can’t make the connection. I don’t know if it is timing out or what. Is there a way to preregister the project which might enable it to make the connection?

舊文章 - 以原文顯示
Paratext [Moderator]
(1.3k 點) 提出

已重新顯示 | 300 次瀏覽

3 個回答

0
最佳回答

There is no way to have Paratext know a project is registered without using the Internet, sorry. They can do an offline migration, but the project will be considered unregistered until they can connect to the internet.

舊文章 - 以原文顯示
[Expert]
(16.7k 點) 提出

Internet improved and they succeeded. But I am still concerned about other situations. You mention an offline migration, but that isn’t possible with a shared project. I was just thinking that there might be a way to pre-register a project, since many projects were pre-registered by their organizations some time ago.

舊文章 - 以原文顯示

You can do an offline migration of a shared project by telling Paratext not to access the Internet by disabling it in Tools > Options (or, slightly more difficult, by having Paratext completely fail to contact the Internet).

舊文章 - 以原文顯示
+1

Would this also be a way that one could rename a project, without having to do the conversion in Paratext 7.6? Basically, turn off the internet in Tools>Options, and then offline migrate, convert the project, delete the initially migrated project, and then register the converted/renamed project?
I tried to test this, and all appeared to work well (I didn’t actually register the project). I am trying to figure out a good way to help people rename improperly named projects, without registering the improper name, and without needing to have them install Paratext 7.6.
Thanks
BEH

舊文章 - 以原文顯示
(418 點) 提出

Yes, that process should work just fine for renaming a project.

Just remember that there is, then, no corresponding project in Paratext 7, so there is no way to re-do the migration and get the same project as a result (i.e. every time Convert Project is used, it will create a new project with a different internal ID). This means, even if you re-converted to the same project name, none of the Paratext servers would “see” it as the same project as the original conversion.

Most of the time, this shouldn’t be an issue, but if you are planning on pre-registering the project before a final migration or something like that, it wouldn’t work.

舊文章 - 以原文顯示

Thanks, that is good information to think about.

舊文章 - 以原文顯示
0

Another issue is if in poor bandwidth the team will be able to do the first send/receive, since it means uploading the entire project to the Paratext 8 server. Often upload speeds are slower than download speeds.

I helped some PNG colleagues migrate because of this issue. They added me as admin to their P7 project, I did the registration and migration and they received the new project from the 8 server. This process could be blocked by pre-registration in 8, because the 8 project won’t have the “new” admin listed as a team member, and cannot register it as a new project. To get past this someone would have to delete the preregistered project from the registry, or add the new admin to it (if it is possible to add a new team member directly to the registry without using Paratext).

舊文章 - 以原文顯示
[Expert]
(3.3k 點) 提出

相關問題

0
1 個回答 172 次瀏覽
我需要協助解決一個語言識別碼的問題 PT 專案 NYYBT 的語言 ID 是 nyy-Latn-002 這應該要與我的 FieldWorks 專案相關聯,該專案中 NYY 的本土文字系統也已設定好 但 PT 專案屬性一直顯示紅色驚嘆號,並提示 ... 對於相關的詞彙專案無效」 兩者明顯都是 nyy 哪裡出錯了?這跟那個「002」有關嗎? 感謝任何在外的協助
anon673293 106 提出 已提問 12月 26, 2023
0
3 個回答 305 次瀏覽
One of my colleagues had difficulty installing Paratext 9; the program suggested contacting support with the attached log ... ! Paratext_9.0.100_20200116015808.log.pdf (55.5 KB)
anon773589 194 提出 已提問 1月 16, 2020
0
0 個回答 188 次瀏覽
To move a book from one difficulty level to another, see either of the following: [How do I change the expected rate ... /520) (the Change the difficulty level of a book section)
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
1 個回答 157 次瀏覽
When I migration Consultant projects, I need to turn on the S/R and then manually re-add in all the users/roles ... Is this how it is supposed to work/migrate? Thanks, listentwice
listentwice 1.2k 提出 已提問 11月 8, 2017
0
2 個回答 348 次瀏覽
We have some projects that have used the Project Progress tool in Paratext 7. In migrating to Paratext 8, is ... ? Can it be transferred into the Project Plan? anon980192
anon980192 119 提出 已提問 11月 2, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
Make every effort to keep the unity of the Spirit through the bond of peace.
Ephesians 4:3
3,045 個問題
6,005 個回答
5,671 則評論
2,026 位使用者