Support.Bible is a public forum that connects users of Bible translation software, so that they can help one another find solutions and discover new ways of working together. We welcome users of all Bible translation software systems to discover how they can help one another take God's Word to the world.
Search existing questions first — if you don't find what you need, create a free account to ask your own.
我收到了一位用户提出的这个问题。欢迎大家提出想法或建议:
有没有办法保存现有的项目计划,以便经文历史(工作进度)不会被删除,并基于一个基础计划创建新的项目计划?我不想丢失经文历史。或者,我是否应该直接对当前计划进行修改,例如为各个阶段添加描述并添加任务?我们已经完成了新约和《创世记》,并开始处理其他旧约书卷。多年前在高级 Paratext 培训课程中建立的项目计划中,既没有描述过的阶段,也没有包含任何任务。
有没有办法保存现有的项目计划,以便经文历史(工作进度)不会被删除,并基于一个基础计划创建新的项目计划?我不想丢失经文历史。或者,我是否应该直接对当前计划进行修改,例如为各个阶段添加描述并添加任务?
我们已经完成了新约和《创世记》,并开始处理其他旧约书卷。多年前在高级 Paratext 培训课程中建立的项目计划中,既没有描述过的阶段,也没有包含任何任务。
I received this question from a user. Thoughts/suggestions welcome:
Is there a way to save an existing project plan so that the verse histories (work progress) are not deleted, and make a new project plan from a base plan? I would like to not lose the verse histories. Or should I just make changes to the current plan, adding descriptions to the stages and adding tasks?We're finished with the New Testament and Genesis, and have started on other Old Testament books. The project plan that was put in place years ago in the Advanced Paratext training course doesn't have any described stages nor tasks included.
Is there a way to save an existing project plan so that the verse histories (work progress) are not deleted, and make a new project plan from a base plan? I would like to not lose the verse histories. Or should I just make changes to the current plan, adding descriptions to the stages and adding tasks?
We're finished with the New Testament and Genesis, and have started on other Old Testament books. The project plan that was put in place years ago in the Advanced Paratext training course doesn't have any described stages nor tasks included.
您可以在 paratext.org 上查找有关如何替换项目计划(Project Plan)的信息
注意:我建议使用任务表(Task table)来保存现有数据,而不是使用阶段表(stages table),因为任务表能提供更详细的信息。
You can find information about how to replace a project plan on paratext.org
Note: I would recommend using the Task table to save the existing data rather than the stages table as it gives more detailed information.