In Paratext 8.0 (and later), you can:

  • See if the work of a translation team is ahead of or behind schedule.
  • See whether the current rate of progress will meet the goals of a project.
  • See a graph showing the finish date for a project based on current progress.

    # From the Project menu, select Progress Charts....
  1. From the "Select View" drop-down list, select Forecast Line Chart.
  2. From the "Show Book to View Progress" drop-down, select one of the following:
    • All Books – to see progress for the entire project.
    • Current Book – to only see progress for the current book.
  3. Optionally: Click the printer icon to print the chart.
  4. Optionally: Adjust the beginning point and/or the ending point of the graph. (See instructions below.)

Adjust beginning and/or ending point of graph

To adjust the beginning point of the graph, click the calendar icon to the right of the “Show from” box and do any of the following:

  • Click the right-arrow or left-arrow to navigate to a date, and then click that date.
  • Click Start of Project to change the beginning point to the date when the project began.
  • Click A Year Ago to change the beginning point to a date one year earlier than the current date.
  • Click Start of Quarter to change the beginning point to the first day of the current quarter.

To adjust the ending point of the graph, click the calendar icon to the right of the “Show until” box and do any of the following:

  • Click the right-arrow or left-arrow to navigate to a date, and then click that date.
  • Click Target Completion (Registry) to change the ending point to the date in the "Expected Completion" box in the Paratext Registry.
  • Click Forecast Completion to change the ending point to the date Paratext calculates that the project will be complete.
  • Click End of Quarter to change the ending point to the last day of the current quarter.

Explanation of the chart

  • Horizontal axis: Displays years and the endpoints display the date in YYYY-MM format.
  • Vertical axis: Displays the percentage of completion.
  • Broken diagonal lines:
    With a square at the upper right: Shows progress relative to the date in the "Expected Completion" box in the Paratext Registry.
    With a triangle at the upper right: Shows the estimated completion based on actual progress.
  • Solid diagonal line: Shows actual progress.
  • Vertical line: Shows the estimated completion date.
舊文章 - 以原文顯示
Paratext [Expert]
(735 點) 提出

已重新顯示 | 141 次瀏覽

登入註冊 以回答此問題。

相關問題

0
0 個回答 135 次瀏覽
If you want an overview of project progress by book, do the following: From the Project menu, select Progress Charts ... since the date one year earlier than the current date.
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
2 個回答 395 次瀏覽
If you want an overview of project progress by stages, do the following: From the Project menu, select Progress Charts. ... since the date one year earlier than the current date.
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
0 個回答 217 次瀏覽
In the project for which you want to see the completion status of tasks: Click to make it the active window. ... "Assignments and Progress" dialog.) You can print the chart.
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
1 個回答 409 次瀏覽
我在這個專案中是管理員。另一位管理員在 GLO 和其他書卷中進行了修改,並執行了 send/receive。她在其他書卷中進行的修改已正確更新,我在執行 send/receive 後可以看到這些變更。但她在 GLO 中進行的修改雖然在「最近變更」和「專案歷史」中對我是可見的,卻未在 GLO 書卷中更新。
anon399461 123 提出 已提問 3月 13, 2024
0
0 個回答 196 次瀏覽
You must have a role on the project to be able to see if it has been uploaded to the DBL. You can see whether ... column. See also: What is DBL (the Digital Bible Library)?
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
Dear friends, since God so loved us, we also ought to love one another.
1 John 4:11
3,051 個問題
6,010 個回答
5,676 則評論
2,030 位使用者