Normally, you should be an administrator to do this.
By default, all administrators, translators, and consultants on a project can mark project progress. However, to ensure consistent decisions, you can prevent some users from marking project progress.

  1. Click in the window of your project, to make it the active window.
  2. From the Project menu, select Users, Roles and Permissions....
  3. Click Other Permissions... below the list of project users.
  4. In the row for each user you want to prevent from marking project progress, click to clear the check mark in the Progress column and click OK when you are done.
  5. Click OK to close the Users, Roles and Permissions dialog.
  6. A reminder appears telling you that you must now do a Send/Receive; click OK.
  7. The Send/Receive Projects dialog appears; click Send/Receive.
舊文章 - 以原文顯示
Paratext 由 [Expert]
(735 點) 提出

已重新顯示 | 306 次瀏覽

請 登入 或 註冊 以回答此問題。

相關問題

0 票
1 個回答 311 次瀏覽
Yes, in the Users, Roles and Permission window click on the Other Permissions button and uncheck the Progress box. In ... or remove permission for certain project tasks? in help.
[Expert]
Jeff_Shrum
2.9k 提出
已提問 5月 10, 2017
0 票
0 個回答 229 次瀏覽
No, unchecking the Progress box in the Users, Roles and Permissions window will not keep a team member from marking ... marking the progress of other team members. [Link Removed]
[Expert]
Jeff_Shrum
2.9k 提出
已提問 5月 10, 2017
0 票
0 個回答 288 次瀏覽
Normally, you should be an administrator to do this. By default, all administrators and translators on a project ... The Send/Receive Projects dialog appears; click Send/Receive.
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0 票
0 個回答 199 次瀏覽
To include a check in a stage of project progress: From the Project menu, select Project Plan.... Click the Checks ... -checks-can-i-include-in-a-stage-of-project-progress/1217)
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0 票
0 個回答 247 次瀏覽
This can only be done by a project administrator. Follow the steps below to specify the books for which ... support.paratext.org/t/introduction-to-project-progress-tracking/292)
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
For just as each of us has one body with many members, and these members do not all have the same function, so in Christ we, though many, form one body, and each member belongs to all the others.
Romans 12:4-5
3,080 個問題
6,047 個回答
5,709 則評論
2,048 位使用者