Follow the steps below to copy a task from the project plan for project ORIG (the “origin project”) to the project plan for project DEST (the “destination project”).

  1. From the File menu, select Open Project/Resource.
  2. Select project DEST and click OK.
  3. From the Project menu, select Project Plan....
  4. At the upper right of the dialog, click Manage Plans....
  5. From the "Show Base Plan" drop-down, select the project plan for the ORIG project.
  6. On the Current Plan side of the dialog (the DEST project side), click the row that has the task which you want to precede the copied task.
    If you want the copied task to be the first task in the stage, select the stage name.
  7. On the Base Plan side of the dialog (the ORIG project side), click the task you want to copy, hover over that task, and click the solid arrow that appears.
    The task is copied to the project plan for the DEST project and becomes unavailable to be copied again to the project plan for the DEST project.
  8. Optional: To move the task, click the up arrow or the down arrow that appears when you hover over a task on the Current Plan side of the dialog.
  9. Click OK to close the "Manage Plans" dialog.
  10. Click OK to close the "Project Plan" dialog.
    The copied task has the same name and progress rate as it had in the project plan for project ORIG.
    If you want to change the progress rate for the copied task, see [How do I change the expected rate of project progress?](http://support.paratext.org/t/how-do-i-change-the-expected-rate-of-project-progress/429)

:checkicon: If you want to delete a task from the project plan, click the task on the Current Plan side of the dialog, hover over that task, and click the X that appears.

:informationicon: See also:

舊文章 - 以原文顯示
Paratext [Expert]
(735 點) 提出

已重新顯示 | 175 次瀏覽

登入註冊 以回答此問題。

相關問題

0
0 個回答 171 次瀏覽
In the window of the project that has the expected rate of progress you want to replace, click to make it ... that will overwrite the values already present for the selected task.
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
0 個回答 180 次瀏覽
If you have been using Assignments and Progress or Big Picture Chart (Experimental) from the Project menu to ... -have-been-made-since-an-earlier-project-progress-stage/272)
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
0 個回答 192 次瀏覽
To move a book from one difficulty level to another, see either of the following: [How do I change the expected rate ... /520) (the Change the difficulty level of a book section)
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
1 個回答 152 次瀏覽
empty empty empty empty empty empty
[Expert]
anon421222
735 提出
已提問 2月 23, 2017
0
2 個回答 384 次瀏覽
We work with translators from a number of dialects. I've just gotten to the point where I've created a separate Project ... Is there a way to migrate Notes to a different project?
Paul 642 提出 已提問 2月 7, 2018
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
Make every effort to keep the unity of the Spirit through the bond of peace.
Ephesians 4:3
3,048 個問題
6,007 個回答
5,672 則評論
2,028 位使用者