0 suara
411 tampilan

I have been assigning dates/deadlines to the various steps of our project plan, but I can’t find where those dates show up anywhere under “Tasks”. It’s not obvious for the team members to go into the project plan details and find these assigned dates, so I’m hoping there is an easy way to get the assigned dates to show up under their individual Tasks tab.

Has anyone else found a way for dates to work well in the project plan?

Thanks!

Postingan lama - ditampilkan dalam bahasa aslinya
Paratext oleh (161 poin) | 411 tampilan

1 Jawaban

0 suara
Jawaban terbaik

jwagner, can you explain where you are assigning those dates? Do you put it in the task name? or the description? or somewhere else?

The current implementation of the project plan does not have a way to show deadline information (except for the project as a whole - and that is in the registry). When a user clicks on Assignments and Progress and then goes to My Tasks they should see the tasks that are currently assigned to them and for which they have editing rights.

I’m not sure how you could add deadlines to tasks since the plan is for the entire project, but the translator sees individual books.

If you have not watched the videos on administering a project plan I’d recommend watching this set found at:
https://vimeo.com/channels/paratext/videos/search:plan/sort:preset
and
https://vimeo.com/channels/paratext/videos/search:assign/sort:preset

Postingan lama - ditampilkan dalam bahasa aslinya
oleh (9,9k poin)

I think he’s talking about the deadlines for each stage per book:

The deadline dates are only for the administrator to make sure progress is happening as expected. The values are currently only used for the Forecast Line Chart (Project > Progress Charts > Forecast Line Chart).

Postingan lama - ditampilkan dalam bahasa aslinya

anon848905,
anon291708 is correct, I thought the deadlines in each stage that forecast the project plan would also be a great help to the team for keeping track of their assignments on multiple books etc…

I can do a screenshot of their Tasks page and write in their deadlines myself, but it seems like a great idea if it can be built right into the project plan.

Thanks for the quick replies, I really appreciate it!

-jwagner

Postingan lama - ditampilkan dalam bahasa aslinya

Feel free to make a feature request for doing something more with that information. :grin:

Postingan lama - ditampilkan dalam bahasa aslinya

Pertanyaan terkait

+1 suara
3 jawaban 374 tampilan
Dengan situasi dunia saat ini, banyak tim penerjemahan kami bekerja secara jarak jauh dan tidak bersama-sama di ... kirim/terima (send/receive) sebenarnya terjadi? Terima kasih.
Stephen Katt 1,3k bertanya Apr 6, 2021
0 suara
3 jawaban 517 tampilan
We are trying to improve the flexibility of how we check numbers and dates in Paratext. This is difficult because there ... not sure, the dialog is not clear 0voters Show results
[Moderator]
IanH
1,2k
bertanya Jun 30, 2015
0 suara
0 jawaban 203 tampilan
Membuat salinan HTML yang dapat dilihat/dicetak dari Rencana Proyek (Project Plan) yang terkait dengan proyek. ... bagus untuk menunjukkan rencana kepada pengguna non-Paratext.
[Moderator]
dhigby
1,3k
bertanya Nov 12, 2021
0 suara
12 jawaban 1,5k tampilan
rencana proyek tidak menunjukkan berapa banyak ayat yang telah draf. Apakah ada cara untuk mengatur pengaturan dalam ... ayat yang telah draf, diuji, dan diperiksa konsultan
anon441204 250 bertanya Mei 1, 2021
0 suara
1 jawaban 336 tampilan
Seorang penerjemah ekspatriat di PNG telah mengatur Project Plan di PT8 beberapa waktu lalu, tetapi tidak berdasarkan ... , apakah penerjemah nasional masih bisa bekerja di PT8?
anon469049 120 bertanya Feb 25, 2021
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
All the believers were one in heart and mind. No one claimed that any of their possessions was their own, but they shared everything they had.
Acts 4:32
3,049 pertanyaan
6,007 jawaban
5,673 komentar
2,029 pengguna