Hi,
I was wondering if there is an option in Paratext to easily view or export a list of the chapters and verses which have been translated?
In Ethnos360, (New Tribes Mission) we are looking at ways to keep all of our translation project up to date in a database, and were wondering if there is a way to generate that report from Paratext?
Thanks
BEH

舊文章 - 以原文顯示
Paratext (418 點) 提出 | 674 次瀏覽

8 個回答

0
最佳回答

BEH,

I looked at the reports/charts available in Paratext. I can see which books, chapters are completed, but I anon421222’t see away to export that information.

And:

Are either of these helpful for you?

anon044949 S.

舊文章 - 以原文顯示
[Expert]
(2.9k 點) 提出
0

From help in Paratext 8.0:
How do I generate a project progress report?

  1. From the Tools menu, select Project Health Report.
  2. On the left of the “Select Texts to View Project Health” dialog, double-click to select the projects for which you want to view project health.
    The names of the stages of the project that is first in the list of selected projects will become the labels of the rows for the “Progress” section in the report.
    If you want to change the order of the selected projects in the list at the right, click to select a project, and then click the up or down arrow.
  3. Click OK.
    The report will contain a column for each project you selected.

The project health report shows the percent of verses completed for each stage of the project, shows the rate of progress, and shows the percent of work completed for other areas (such as project notes which are resolved).

舊文章 - 以原文顯示
[Expert]
(735 點) 提出
0

Thanks for the answer.
Unfortunately, that isn’t what I am looking for. I am more looking for something that will have a list of what has been done, (i.e. chapter and verse ranges that are in progress or completed) not just percentages of the whole, etc
Thanks
BEH

舊文章 - 以原文顯示
(418 點) 提出

No, sorry, there is no straightforward way to generate a report like that.

舊文章 - 以原文顯示
0

One of the main objectives of Paratext 8 was to allow better tracking of projects by administrators. dhigby has written a description of this on the Paratext 8 website.
Project Tracking in Paratext 8

You should explore what this new system is able to do, and how your organization could exploit the new API to access the database . The intention was for organizations to have access to the data. I am unclear if there is one Dashboard that everyone must use, or if the API would allow one to connect an in-house system to the database.

舊文章 - 以原文顯示
[Expert]
(2.9k 點) 提出

Thanks,
I have been looking into that, and talking to some of our consultants about it as well, but it is a slow process.
Knowing that Paratext already outputs the opposite of what I was asking about, i.e. it will give a list of verses that are missing, I was wondering about the feasibility of having a check that would show a list of what is there. Would that be something that one could make with a custom check? If so, could you point me in the right direction on how to go about starting that? (I am thinking I recall something about some custom checks that can be made)
Thanks
BEH

舊文章 - 以原文顯示

Hi BEH,

Our progress reporting focuses on books, with some level of indicating chapters. The problem with asking to see “chapters and verses which have been translated” is that, while it is feasible to show a list of chapters and verses with text, that won’t show you anything about the quality of that text. That is why we have progress.paratext.org and the API which allow you to see which books are at which level of completion. The API may allow your organization to design a tool that can analyze the data in the way that you want.

舊文章 - 以原文顯示
0

Thanks for the info.
One of the main issues is that many of our users are not very Paratext literate. That is something we are working to try to remedy, but in the meantime, …
Thanks for all the suggestions.
BEH

舊文章 - 以原文顯示
(418 點) 提出
0

I personally think BEH has raised a very valid consideration. It seems to me that there are (at least) two approaches possible when collecting progress data. You can track “raw” data (which is what BEH seemed to be asking for) and then have data points for every single user, but not have very granular (or detailed) information about each project. In this case, you might only know whether “some text” exists for a given verse, but not know anything about the quality of that text. The other approach (that Paratext has taken) is to only consider highly detailed information (coming out of the progress tracking tool), and accept that a large number of users may choose to not use that tool, so your dataset will be much smaller. I personally think it would very valuable to track both sets of data.

I also think it would have been wiser to promote a much simpler default project plan, to lower the bar for entry into the Assignments and Progress tool. People can always add more detail to their plan after they start to use it, but if it appears too difficult when it is first introduced, they will be more likely just give it a miss entirely, and then the opportunity have data related to that project is lost.

anon101508 G.

舊文章 - 以原文顯示
(117 點) 提出

anon101508,

I would like to respond to your comment on the default plan, if you are referring to the SIL plan. I cannot comment on any other organizations plan. The thinking was to make a very comprehensive plan to show what is possible, and allow people to delete what they did not want. I would be interested to know if people are so overwhelmed by it that they do not even attempt a plan.

anon044949

舊文章 - 以原文顯示
0

Regarding the plans, I really like the plan functionality, and have begun doing a few things with the plan. However, I am not in a decision making role regarding what exactly we in our organization should have in our plans etc., Also, most of our consultants did their translation work before Paratext, and are just now getting more Paratext literate. Now several of them have begun doing consultation directly in Paratext, so I would anticipate that they will now be more ready to put together a plan, and we can begin using the progress tracking features.
One issue that I do see is that it is difficult to report the progress of previously completed material. For instance, as a part of a project plan, we would like to include the BT checks, etc. However, much of our material (which was translated and then imported into Paratext), doesn’t have a corresponding BT. At present, I anon421222’t see a way to “grandfather” in parts of a project that were previously completed. For example, about half of our NT in my project was translated before we started using Paratext. So, the BT is not there, though the material is finished and printed. I anon421222’t really see any straightforward way to mark those books as complete. I think I could remove the BT checks, mark the progress as complete, and then add the BT checks back into the project plan, but that gets complicated for most users.
I really think the project tracking features are great, but the implementation is something that will take some time, at least in our case.
BEH

舊文章 - 以原文顯示
(418 點) 提出
0

BEH,

We are getting far from the original topic. I have writing a blog article on marking progress on “mature” projects after they have been moved to Paratext 8. You should be able to find that. Beyond that I suggest you post a new question to this site about dealing with Back translations of projects that are well underway when they are migrated. I would comment on that and maybe others will too. This topic will get lost here and many will not see it.

anon044949

舊文章 - 以原文顯示
[Expert]
(2.9k 點) 提出

I will put that in another topic, thanks.
Incidentally, can you point me to the blog article you are writing, or is that something in the works?
Thanks again.

舊文章 - 以原文顯示

相關問題

0
1 個回答 562 次瀏覽
2016-07-28 20:44,我在標題為「從 Paratext 線上儲存庫還原文字?」的帖子中寫給 PT 支援者: 如果我想查看專案歷史中先前時間點的章節,我不會還原到每個時間點 相反地,我會使用 Compare Texts 功能,它允許您查看 ... 言,我希望有一種簡單的方法,能夠對先前版本執行所有您可以對目前文字執行的操作 這值得提出功能請求嗎?
wdavidhj 1.4k 提出 已提問 7月 28, 2016
0
1 個回答 254 次瀏覽
我正在培訓顧問,其中一位 CiT 正在觀察我如何以顧問身分檢查專案 她已被設為觀察者 不幸的是,觀察者無法建立對照譯文,而且也沒有可用的回譯 起初,我將對照譯文工具(interlinearizer)列印成 PDF 給她 但後來我聽說可以 ... 試這樣做,但儘管有一個「將註釋(glosses)輸出至專案」的選項框,我卻無法勾選它 這是否僅限於管理員才能操作?
nomadic consultant 169 提出 已提問 2月 15, 2023
0
1 個回答 427 次瀏覽
我想將專案匯出為 HTML,以便與他人分享草稿 我不想匯出為 PDF,因為 PDF 在智慧型手機和其他小螢幕裝置上操作起來相當不便 我可以透過開啟 Paratext,點擊專案選單按鈕,然後選擇「進階」(Advanced),再選擇「將專案 ... 而,USFM 標記是可見的,例如 \v 1 和 \s 等標記 我該如何隱藏匯出 HTML 中的 USFM 標記?
bit 495 提出 已提問 4月 14, 2022
0
2 個回答 323 次瀏覽
我正在處理一個從右至左(RTL)專案轉換為從左至右(LTR)的音譯專案 不知何故,PDF 匯出中數字周圍標點符號的方向有時會反轉 在 Paratext 中一切看起來都正常,例如: 但在 PDF 匯出中,它看起來像這樣: 有時是正常的,但通常非常 ... 專案中沒有觀察到這種行為,只有在音譯專案中才會出現 是否有一些從來源專案遺留下來 需要我更改的設定?
DVM 175 提出 已提問 7月 8, 2021
0
3 個回答 544 次瀏覽
各位朋友好, 我有一份經文引用清單,標記如下(請注意,在 Ptxt 中這是右對齊的,所以標記位於最右側--也就是行首的位置): (6:ISA 53)1$ nb\ 最終,我希望將我的清單(來自 SAB - Sharif Arabic ... 其他幾個小問題,但我猜應該有一個地方可以識別並設定所有要匯出的功能 那會是在哪裡呢? anon303076 (SAB)
anon303076 118 提出 已提問 3月 25, 2021
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
Very truly I tell you, whoever accepts anyone I send accepts me; and whoever accepts me accepts the one who sent me.
John 13:20
3,045 個問題
6,005 個回答
5,671 則評論
2,026 位使用者