Last day of a PT8 Migration workshop.

We needed to delete the User1 PT8 account. After we made User 2 admin on the project and removed User1 from all projects, then the PT8 registry allowed us to delete the User1 account.

Now the PT8 registry shows User2 as admin, and does not list User1 on the project. Success we thought. However, on User2 computer it shows User2 as observer, and still lists User1 as the only admin.

I think the internet was flaky when then were making user access changes on User1’s computer. The registry history shows they changed User2 to Observer and then to Admin.

Rebooting User 2’s Computer did not help. Deleting the project from User2’s system, and doing a S/R did not help.

User2 is the only Admin. There is one translator but they are not local and have not setup a PT8 account yet.

Need some help!

My last resort would be to ask UBS to delete everything on PT8 servers and we could redo the migration, but I would rather not.

Thanks, listentwice

Paratext by (1.2k points) | 307 views

2 Answers

0 votes
Best answer

If you send me specific project and user information, I may be able to help. Make sure that user account has the current Paratext code. When changing names and deleting accounts, you need to be sure that the computer has the correct name and registration code, and not the old one that was in there before.

by [Moderator]
(1.3k points)

reshown
0 votes

It is fixed. Thanks!

by (1.2k points)

Related questions

0 votes
2 answers 191 views
Is it possible to quickly delete projects by deleting their folder from My Paratext 9 Projects, instead of opening each ... them in the Registry or S/R server. Thanks, james_post
[Moderator]
james_post
2.1k
asked Jun 17, 2022
0 votes
6 answers 792 views
I am working with two projects. On one computer I want to add to the admin account two user accounts for these ... even that the new registration goes back to the admin account.
anon057624 136 asked Jun 25, 2021
0 votes
2 answers 214 views
I have a remote team member, who now can't continue working on our project, since I attached the new compact plan ... s/r declared the project no longer compatible) was still lost.
ChrDre 255 asked Jan 8, 2020
+1 vote
4 answers 703 views
A long standing issue is when translators have a FLEx project connected to their PT Project, and the PT Admin ... lack of linguistic SW being installed/configured on their system.
listentwice 1.2k asked Jun 9, 2022
0 votes
1 answer 161 views
I change two usernames in the registry, and they both lost most of the projects in their S/R window. Went for 20+ ... I have done S/R, looked at registry, everything looks correct.
listentwice 1.2k asked Mar 13, 2023
Welcome to Support Bible, where you can ask questions and receive answers from other members of the community.
May the God who gives endurance and encouragement give you the same attitude of mind toward each other that Christ Jesus had.
Romans 15:5
3,037 questions
5,994 answers
5,661 comments
2,022 users